How to Calculate materials Quantity for Plastering Work

In this tutorial, we will analyse how much materials such as cement and sand are needed for plastering work. Take a look at step-by-step guidelines on how to calculate the cement sand quantity for plastering.

Mortar ratio = 1:6 where 1 is cement and 6 part is sand.

How to calculate cement sand quantity for plastering

Plaster thickness = 12 mm = 0.012 m

Cement density = 1440 kg/m3

1 m3 = 35.3147 ft3

Suggested Plaster Thickness

12 mm for internal walls or brick wall plain surface
15 mm for 4” or 9” brick wall rough surface 20 mm for two plaster layers normally utilized for external walls

Mortar Wet volume = 1 x 1 x 0.012 = 0.012 m3
Mortar Dry volume = 0.012 x 1.30 = 0.0156 m3

Mortar Dry volume (sand + cement) = 30 – 35 % greater than wet volume = wet volume x 1.30
Concrete Dry volume (aggregate + sand + cement) = wet volume x 1.54

As we know that mortar ratio = 1:6, from which 1 + 6 = 7 = sum of ratio
Amount of cement in plaster = 1/7 x 0.0156 x 1440 = 3.21 kg

Also in bags = 3.21/50 = 0.064 bag = approximately 1 bag
Amount of sand in plaster = 6/7 x 0.0156 = 0.0133 m3
Sand quantity in cubic feet = 0.0133 x 35.3147 = 0.47 ft3